Description
NTDI21-A Using the setup shown in FIGURE 7–9: General test setup on page 7–25 with the Interval
Timer enabled,
Set the current level to 1.5 times the element operate level and apply
suddenly by closing the double-pole switch.
Record the operate time and NTDI21-A compare to the S4 ELEMENTS GROUND
OC W1 GND INST OC 1 W1 GND INST OC 1 DELAY value.
7.5.11.5 Winding 2 or 3 Element
Because the winding 2 and 3 elements can be set with completely different parameters
than the winding 1 elements, it is necessary to NTDI21-A repeat the full set of tests described in this
section for each winding.
Note
Only two ground instantaneous overcurrent 1 elements can be in service
simultaneously.
Note
The blocking from logic input, if enabled, can be tested as described in earlier tests for
other elements.
7.5.12 Ground Instantaneous Overcurrent 2
The ground instantaneous overcurrent 2 elements are identical to the ground
instantaneous overcurrent 1 elements. Consequently, the same test NTDI21-A procedure may be
used to verify their correct operation. Disable all protection features except ground
instantaneous overcurrent 2. Make the appropriate changes for the display indications
and output relays operated by the ground instantaneous overcurrent 2 elements.
7.5.13 Restricted Ground Fault Polarity Test
This procedure verifies the correct wiring of field CTs (phase and ground) to the
corresponding phase and ground CT terminals on the relay for the purposes of the
restricted ground fault protection. The correct wiring is determined by the distribution of
fault current during external phase A to ground faults on wye-connected windings with
grounded neutral.
From the figure below, the I f fault current travels NTDI21-A through the wye-grounded neutral as I g
and can be simulated by injecting a single current into the phase A (W2) and G1/2
terminals.
The procedure for this test is shown below:
Select the D/Y30° transformer type into the relay and set the same CT
ratio for both phase and ground winding inputs.
The selected transformer type assures the G1/2 ground input is
associated to winding 2 (wye).
Enable the restricted ground fault protection only and monitor the
ground differential current under the relay actual values.
Connect the single current source to inject current into G10 of the
ground G1/2 terminal and to the connected in-series winding 2 phase A
terminals as shown on the figure above.
Verify the ground current and phase A current are in phase
Verify the ground differential current is zero
Note
The polarities and wirings of the CTs for the restricted ground fault protection are correct if
the external phase-to-ground fault current is seen on both relay terminals (phase and
ground) in the same direction. The response of the restricted ground fault protection is
based on the magnitude of the ground differential NTDI21-A current resulting from the vector
difference of the neutral and ground currents; that is, .
7.5.14 Restricted Ground Fault Element Test
7.5.14.1 Description
This procedure verifies that the restricted ground fault performance matches the in
service settings. The ground element measures the current signal connected to the ground
current input CT, H10 and G10 or F12 and E12. The neutral (3I o) current is calculated from
the vector sum of the three phase currents. Injecting current into one phase automatically
produces a neutral current (i.e. 3I o = I A). Settings for these elements are found in the S4
ELEMENTS RESTRICTED GROUND W1(3) RESTD GND FAULT setpoints menu.
7.5.14.2 Winding 1 Element
To ensure that only the restricted ground fault element operates the trip relays (and any
other output relays selected by the logic) disable all protection features except restricted
ground fault.
Using a current supply as shown in the figure below, connect the I 1 current source to
terminals H1 and G1 for the winding 1 phase current element and I 2 to terminals G10 and
H10 as shown for the ground current element. Monitor the appropriate output relays as
per the relay FlexLogic™ settings or assigned relay settings.
Why are the prices of many products of our company more competitive?
(1) Source purchase to reduce the price difference in the intermediate phase
(2) Stable channel and more guaranteed supply
Lead time problem
(1) For the spot products in stock, the delivery can be arranged on the same day after the contract payment is signed
(2) Order products and deliver according to the quoted delivery date
Xiamen Xiongba adheres to the enterprise philosophy of “improving the value of spare parts supply chain”,
For the simple purchase procedure of spare parts, ensure that they are delivered to the site in a timely manner, and help users reduce the risk of downtime caused by the shortage of spare parts
The emergency spare parts support service is complete, and the user can customize the spare parts. The quality of the spare parts is reliable. All the spare parts provided enjoy a one-year super long warranty
Spot stock, fast response, reduce user capital investment, improve spare parts utilization, spare parts replacement!
Details: If you need urgent delivery orders, please feel free to contact us, and we will try our best to meet your needs.
Price problem: If you find that other suppliers offer cheaper prices for the same product, we are also willing to provide you with reference prices and give you further discounts.
Contact us:+86 180 6092 3929
Mail: 2235954483@qq.com
Contact: Chen