Description
GE General Electric Technical Specifications: IS200VVIBH1A
IS200VVIBH1A Test Connections per Figure 17–1: RELAY TEST WIRING – WYE CONNECTION or Figure 17–2: RELAY
TEST WIRING – DELTA CONNECTION on page 17–4.
Procedure To Check:
IS200VVIBH1A Minimum Operating Voltage Supervision:
- Set the injection source well below the pickup frequency. Inject Va = 0 V into the bus voltage input of the
relay with Ia = Ib = Ic above the Minimum Operating Current level. The PICKUP indicator should be off.
- Slowly increase the voltage in phase A until the PICKUP indicator comes on. Check that the pickup voltage
is the selected Minimum Operating Voltage.
- Slowly reduce the voltage. Note the voltage at which the PICKUP indicator goes out. Check that this drop
out voltage is the pickup voltage minus 2 x VT nominal. Turn the injection voltage off.
brand | Product Name | Product model | Order No |
GE Fanuc | Module card | IS200VVIBH1A | nothing |
Place of Origin | Marketable land | Imported or not | defects liability period |
Europe and America | Nationwide and overseas | yes | a year |
Place of shipment | Delivery method | How to use | Applicable industries |
Xiamen | Shunfeng Express | Commissioning and installation | Power Plant Steel Plant Cement Plant Shipboard Papermaking |
Service advantages | Foreign import, goods preparation and supply | Reasonable price and reliable quality | Pictures are for reference only |
Product features | Primary source of goods, supply by model | After sales guarantee | Chen 1810693-7731 |
IS200VVIBH1A Minimum Operating Current Supervision:
- Set the injection source well below the pickup frequency. Inject Va = 0 V into the bus voltage input and Ia =
Ib = Ic = 0 A into the phase current inputs of the relay. The PICKUP indicator should be off.
- Slowly increase the voltage in phase A above the selected Minimum Operating Voltage. The PICKUP indi
cator should remain off.
- Slowly increase the phase A current until the PICKUP indicator turns on. This is the Minimum Operating
IS200VVIBH1A Current level. Now reduce the current until the PICKUP indicator turns off. Note the dropout level, which
should be 2% of CT less than the Minimum Operating Current level when the level is ≤ CT. When the Min
imum Operating Current level is > CT, the dropout level should be 97 to 98% of the Minimum Operating
Current level.
- Slowly increase the phase B current until the PICKUP indicator turns on. This is the Minimum Operating
Current level. Now reduce the current until the PICKUP indicator turns off. Note the dropout level, which
should be 2% of CT less than the Minimum Operating Current level when the level is ≤ CT. When the Min
imum Operating Current level is > CT, the dropout level should be 97 to 98% of the Minimum Operating
Current level.
- Slowly increase the phase C current until the PICKUP indicator turns on. This is the Minimum Operating
Current level. Now reduce the current until the PICKUP indicator turns off. Note the dropout level, which
should be 2% of CT less than the Minimum Operating Current level when the level is ≤ CT. When the Min
imum Operating Current level is > CT, the dropout level should be 97 to 98% of the Minimum Operating
Current level.
Why are the prices of many products of our company more competitive?
(1) Source purchase to reduce the price difference in the intermediate phase
(2) Stable channel and more guaranteed supply
Lead time problem
(1) For the spot products in stock, the de
livery can be arranged on the same day after the contract payment is signed
(2) Order products and deliver according to the quoted delivery date
Xiamen Xiongba adheres to the enterprise philosophy of “improving the value of spare parts supply chain”,
For the simple purchase procedure of spare parts, ensure that they are delivered to the site in a timely manner, and help users reduce the risk of downtime caused by the shortage of spare parts
The emergency spare parts support service is complete, and the user can customize the spare parts. The quality of the spare parts is reliable. All the spare parts provided enjoy a one-year super long warranty
Spot stock, fast response, reduce user capital investment, improve spare parts utilization, spare parts replacement!
Details: If you need urgent delivery orders, please feel free to contact us, and we will try our best to meet your needs.
Price problem: If you find that other suppliers offer cheaper prices for the same product, we are also willing to provide you with reference prices and give you further discounts.
Contact us:+86 181 0693 7731
Mail: 2872270648@qq.com
Contact: Chen