5SHY3545L0014 3BHB013085R0001 3BHE039203R0101 GVC736CE101 Control Pulse Card
The provided information discusses the basic functionality and operation of time delays with corresponding relay output signals in a switching sequence. Additionally, it introduces the concept of Bi-Directional Control Thyristors (BCT) developed by ABB Semiconductors. Here are the key points:
Automatic Switching Sequence:
- Anomaly on SOURCE 1:
- An anomaly occurs on SOURCE 1.
- Override Momentary S1 Outage Delay:
- Override momentary delay for SOURCE 1 outage.
- Generator Start:
- Generator starts.
- SOURCE 2 OK:
- Confirmation that SOURCE 2 is operational.
- Transfer from S1 to S2 Delay:
- Delay before transferring from SOURCE 1 to SOURCE 2.
- Pre-Transfer Signal On:
- Pre-transfer signal activates.
- Load Shed Signal On:
- Signal for shedding load activates.
- Pre-Transfer S1 to S2 Delay:
- Delay before transferring from SOURCE 1 to SOURCE 2.
- Load Shed Delay:
- Delay for shedding load.
- Transfer Switch (SOURCE 1) to Position O:
- Transfer switch from SOURCE 1 to OFF position.
- Center-off Delay:
- Delay in center-off position (if Delayed transition I – O – II type).
- Transfer Switch (SOURCE 2) to Position II:
- Transfer switch to SOURCE 2 position.
- Post-Transfer S1 to S2 Delay:
- Delay after transferring from SOURCE 1 to SOURCE 2.
- Pre-Transfer Signal Off:
- Pre-transfer signal deactivates.
5SHY3545L0014 3BHB013085R0001 3BHE039203R0101 GVC736CE101 Control Pulse Card
Re-Transfer Sequence:
- SOURCE 1 is Restored:
- Normal operation resumes on SOURCE 1.
- Transfer from S2 to S1 Delay:
- Delay before transferring from SOURCE 2 to SOURCE 1.
- Pre-Transfer Signal On:
- Pre-transfer signal activates.
- Pre-Transfer S2 to S1 Delay:
- Delay before transferring from SOURCE 2 to SOURCE 1.
- Transfer Switch (SOURCE 2) to Position O:
- Transfer switch from SOURCE 2 to OFF position.
- Center-off Delay:
- Delay in center-off position (if Delayed transition I – O – II type).
- Transfer Switch (SOURCE 1) to Position I:
- Transfer switch to SOURCE 1 position.
- Load Shed Signal Off:
- Load shed signal deactivates.
- Generator Stop Delay:
- Delay before stopping the generator.
- Post-Transfer S2 to S1 Delay:
- Delay after transferring from SOURCE 2 to SOURCE 1.
- Pre-Transfer Signal Off:
- Pre-transfer signal deactivates.
- Generator Stop:
- Generator stops.
- SOURCE 2 Off:
- SOURCE 2 is turned off.
5SHY3545L0014 3BHB013085R0001 3BHE039203R0101 GVC736CE101 Control Pulse Card
Bi-Directional Control Thyristor (BCT):
- ABB Semiconductors has developed the Bi-Directional Control Thyristor (BCT) concept.
- It involves integrating two anti-parallel high-power thyristors onto a single silicon wafer, assembled into one housing.
- Aimed at static VAr compensators, static switches, soft starters, and motor drives.
- Developed using 4“ and 5“ silicon technology with a product matrix of 73, 84, 96, and 118 mm wafers and voltages from 1800 V to 6500 V.
- Release of 4“ devices in 1998, with 3“, 3.5“, and 5“ devices planned for 1999.
Product Philosophy and Quality:
- BCT design, mechanical aspects, manufacturing, and testing follow the same technology and philosophy as ABB’s Phase Control Thyristors (PCTs).
- Flexibility in irradiation and testing processes allows for adapted standard devices.
- Assures high quality, reliability, and compatibility with PCTs.
Complement to PCT Family:
- The BCT family complements ABB Semiconductors’ existing PCT family.
- Resources in application, customer technology, rating, and evaluation have increased to support customer demands with a competitive product range.
Contact us:
Details: If you need an urgent delivery order, please feel free to contact us, and we will do our best to meet your needs.
Price issue: If you find that other suppliers offer a cheaper price for the same product, we are also willing to provide you with a reference price and give you further discounts.
Contact Us:+86 18106937731
Whatapp:+86 15359293870
Email: geabbdcs@gmail.com / 2872270648@qq.com
Contact Person: Chen