This section shows how to install and remove the individual modules (includ
ing I/O modules) in a 3500 rack.
In all discussions, the main module is the part that gets installed in the front of
the rack-mount and panel-mount racks or in the bottom of the bulkhead rack.
They have the blue overlays with the model number printed on them.
The input or I/O modules are the parts that get installed at the rear of the rack
mount and panel-mount racks or in the top of the bulkhead rack. This is where
the power and field wiring connections are made.
4.1 Installation of Modules
The following section describes how to install modules in a 3500 rack. It is
assumed that the applicable slot is empty. Power to the rack does not need to
be removed before installing a module if the procedures below are followed.
4.1.1 Power Supplies
The following lists general steps for installing the 3500/15 power supplies.
Refer to the specific manual for the power supply for details and safety consid
erations. Verify that the main module and the Power Input Module (PIM) are
compatible before proceeding.
- Install the PIM.
– Configure the PIM for Single Point Ground, if necessary.
– Attach power cord to the PIM, if it is deemed to be more convenient at
this time. Be sure that the power cord is not live.
– Place the PIM into place at the back (or top for bulkhead racks) of the
rack. Tighten the screws to pull the PIM securely against the rack.
- Install the main module.
– Slide the main module into place. Ensure that the module is properly in
the guides provided on the rack.
– Tighten the screws securely.
brand | Product Name | Product model | Order No |
BENTLY | modular | 102351-04-01 | nothing |
Place of Origin | Marketable land | Imported or not | defects liability period |
Europe and America | Nationwide and overseas | yes | a year |
Place of shipment | Delivery method | How to use | Applicable industries |
Xiamen | Shunfeng Express | Commissioning and installation | Power Plant Steel Plant Cement Plant Shipboard Papermaking |
Service advantages | Foreign import, goods preparation and supply | Reasonable price and reliable quality | Pictures are for reference only |
Product features | Primary source of goods, supply by model | After sales guarantee | Chen 1810693-7731 |
The following lists general steps for installing any full-height 3500 module.
Refer to the specific manual for the module for details and safety consider
ations. Verify that the main module and the I/O module are compatible before
proceeding.
- Install the I/O module.
– Configure the I/O module for available options, if necessary.
– Place the I/O module into place at the back (or top for bulkhead racks)
of the rack. Tighten the screws to pull the I/O module securely against
the rack.
– Attach field wiring to the I/O module, if appropriate at this time.
- Install the main module.
– Ensure that the ejectors are in their normal position, flush with the front
of the module.
– Slide the main module into place, ensuring that they are properly in the
guides provided on the floor and roof of the rack chassis
– Tighten the screws securely.
- Verify operation.
Note:
It is important to tightly secure the thumb screws to
ensure each module is Chassis grounded. Loose
thumb screws may allow noise to show on the channel
readings.
Why are the prices of many products of our company more competitive?
(1) Source purchase to reduce the price difference in the intermediate phase
(2) Stable channel and more guaranteed supply
Lead time problem
(1) For the spot products in stock, the delivery can be arranged on the same day after the contract payment is signed
(2) Order products and deliver according to the quoted delivery date
Xiamen Xiongba adheres to the enterprise philosophy of “improving the value of spare parts supply chain”,
For the simple purchase procedure of spare parts, ensure that they are delivered to the site in a timely manner, and help users reduce the risk of downtime caused by the shortage of spare parts
The emergency spare parts support service is complete, and the user can customize the spare parts. The quality of the spare parts is reliable. All the spare parts provided enjoy a one-year super long warranty
Spot stock, fast response, reduce user capital investment, improve spare parts utilization, spare parts replacement!
Details: If you need urgent delivery orders, please feel free to contact us, and we will try our best to meet your needs.
Price problem: If you find that other suppliers offer cheaper prices for the same product, we are also willing to provide you with reference prices and give you further discounts.
Contact Us:+86 18106937731
Whatapp:+86 15359293870
Email: geabbdcs@gmail.com / 2872270648@qq.com
Contact Person: Chen